In Progress 📍 Greenstone Hill, Gauteng

Greenstone living room renovation and extension

Marz is carrying out a living room renovation and extension, including wall and tile removal, structural beam installation, floor construction, ceiling work and finishes. Follow the project from the original rooms through demolition and ongoing construction.

Project Timeline

Start Date: 1 October 2026
Expected completion: 24 November 2026
Documented Photos: 9 photos
Latest Progress Update Updated: 13 October 2026

Wall demolition and removal of the existing tiles are complete. The structural beams have been installed, the floor has been filled and the concrete slab poured. Ceiling installation and Rhinolite finishing are now complete. Plaster repairs around the demolished wall areas are being carried out.

Project Scope & Details

Programme Reference for the Vaughn Project

Living room renovation and extension including wall and tile removal, structural steel beam installation, floor construction, ceiling work and finishes.

Remaining Programme Baseline

  • Ceiling drying and painting: Drying to 14 October; paint 15-16 October
  • Wall drying and painting: Drying to 19 October; paint 30 October
  • New aluminium doors and laundry screen: 28-30 October
  • Floor readiness then tiling and grouting: Readiness to 6 November; tiles 9-13 November
  • TV panelling and floating shelves: 16-17 November
  • Electrical finishing and testing: 18 November
  • Final clean and handover: 19-20 November
  • Snag rectification: 23-24 November